Target meeting: 19Aug09, 09:00

Present: ME, MC, RN, PS, PH, JL, CB, KL, AN, EMcC

1. Review of actions:

2. Progress on mechanical design and fabrication:

2.1 Target assembly: AN

2.2 Stator: CB

2.3 Modifications to gate valve and vacuum vessel: EMcC

3. Progress on electrical installation etc.: SG

4. Progress on (dynamic) mechanical FEA: SY, WL

5. Progress on magnetic FEA: PS

6. Target electronics and DAQ: PS, JL

7. Target interaction with MICE PPS and ISIS BPS: CMacW

8. Commissioning plan: PH

9. Next meeting

10. AoB

Summary of actions: